Total M-Books
15
This project
Draft
2
QS entry pending
Submitted
9
Queued for RA Bill
Locked / Billed
3
In closed RA Bills
M-Book List — Tata Networking
🧪
IS 456 Cl.15.2 — Cube sampling check
Pour PC-020 actual volume: 18.75 m³. Required: 1 set × 4 cubes minimum. Site recorded: 4 cubes (Set A). ✓ Compliant. 28-day results pending — enter in Cube Results tab.
Measurement entries (No. × L × B × H)
| Description | No. | L (m) | B (m) | H (m) | Qty (m³) | Remarks | |
|---|---|---|---|---|---|---|---|
| 9.18 | |||||||
| 9.59 | |||||||
| Total measured qty | 18.77 | ||||||
Measured by (QS)
Date:
Checked by (Sr. QS / PM)
Date:
Client / Engineer sign-off
Date:
⚠️
—
—
QS Review Checklist
| Check | Status | |
|---|---|---|
| Measured qty matches pour facts | ✓ Checked | |
| BOQ split total = actual poured qty | ✓ Matched | |
| IS 456 Cl.15.2 cube sampling compliant · Tested per IS 516 | 4 cubes ✓ | |
| Over-measurement check (≤105% BOQ) | None | |
| 28-day cube results confirmed | Pending | |
| Quality hold from NCR | Review pending | Flagged |
BOQ Cumulative Impact
| BOQ item | Contracted | Previous | This M-Book | New total | % |
|---|---|---|---|---|---|
| RCC-COL-M25-BLKC | 220.00 | 126.25 | 9.18 | 135.43 | 62% |
| RCC-COL-M25-CORE | 88.50 | 54.00 | 9.59 | 63.59 | 72% |
🪵
Formwork M-Book — FMB-2026-031
Measures formwork contact area (m²) per element. Each formwork M-Book links to the element's pour card and the Formwork BOQ item. Quantity is measured face-by-face as No. × L × H.
FMB-2026-031
PC-2026-03-027
COL-A1-FL02 · Column
Column · Plywood
FW-COL-BLKA
R. Suresh
Formwork Faces (No. × L × H)
| Face / Description | No. | L (m) | H (m) | Area (m²) | Deduct (m²) | Net (m²) | |
|---|---|---|---|---|---|---|---|
| 0.522 | 0.522 | ||||||
| 0.522 | 0.522 | ||||||
| 0.522 | 0.522 | ||||||
| 0.522 | 0.522 | ||||||
| Total formwork area (net): | 2.088 | ||||||
Measured by (QS)
Date:
Checked by
Client sign-off
Formwork BOQ Cumulative Impact
| BOQ Item | Contracted | Previous | This FMB | New total | % |
|---|---|---|---|---|---|
| FW-COL-BLKA | 2,000 m² | 850.0 | 2.088 | 852.09 | 42.6% |
Formwork M-Book List
FMB No.ElementArea (m²)Amount (₹)Status
FMB-2026-018COL-A1-FL01 · Column6.302,646Locked
FMB-2026-022SLB-A-FL01 · Slab93.1835,408Submitted
FMB-2026-031COL-A1-FL02 · Column2.088—Draft
BBS — Reinforcement Schedule
Linked BBS from CADS India · Element: COL-A1-FL02 · Pour Card: PC-2026-03-027
🔩 CADS India
BBS — COL-A1-FL02 · Column Block A FL-02
Imported 13 Apr 2026
Total: 29.84 kg · Fe500
| Mark | Dia | Shape | Description | No. | Cut L (mm) | Unit Wt (kg/m) | Total (kg) | Verified |
|---|---|---|---|---|---|---|---|---|
| B01 | T16 | Type 38 | Main vertical bars — full height Grid A1 · Lap splice at FL-02 | 4 | 4,820 | 1.578 | 6.31 | ✓ OK |
| B02 | T12 | Type 01 | Intermediate vertical bars 4 nos/face · 125mm spacing | 8 | 4,620 | 0.888 | 7.10 | ✓ OK |
| B03 | T8 | Type 60 | Stirrups / links 100mm confinement · 200mm general | 22 | 1,960 | 0.395 | 8.69 | ✓ OK |
| B04 | T16 | Type 38 | Lap bars — tension splice Lap 640mm · IS 456 Cl.26.2.5 | 4 | 840 | 1.578 | 5.32 | ⚠ Check |
| B05 | T10 | Type 00 | Starter bars — next floor 500mm projection · IS 456 Cl.26.2.3 | 4 | 980 | 0.617 | 2.42 | ✓ OK |
| Total · Fe500 · IS 1786:2008 | 42 bars | 29.84 kg | ||||||
Pre-pour check (Cl.12.1): On-site reinforcement must match BBS before pour can commence. Bar B04 lap length flagged — verify 640mm is achieved on site before checklist item "Reinforcement — placement, laps & BBS check" is marked OK.